IDENTIFICATION AND CONTROL OF HAZARDS AT CONSTRUCTION SITES

SR NOCONSTRUCTION ACTIVITYASSOCIATED HAZARDSEFFECT OF HAZARDSPREVENTIVE MEASURES / RECOMMENDATIONS
1Electrical installations and usageShort CircuitingElectrocution or fireUse hand gloves & other PPE
Don’t lay wires under carpets , mats or door ways
Employ licensed electricians to carry out electrical installation
Use one socket for one appliance.
Ensure usage of only fully insulated, undamaged wires or cables.
Don’t place bare wire ends in a socket
Ensure earthing of equipments
Do not use damaged cords and avoid temporary connections
Provide all connections through ELCB
Protect electrical cables / equipments from water and naked flames.
Check all connections before energizing.
Over loading of Electrical systemBursting of system leading to fireDisplay voltage and current ratings prominently with Danger signs.
Ensure approved cable size, voltage grade and type
Switch of the electrical utilities when not in use.
Do not allow unauthorized connections.
Ensure proper grid wise distribution of power.
Improper laying of overhead under ground transmission lines / cablesCan cause electrocution and prove fatalDo not lay unamoured cable directly on ground, wall, top of trees. Maintain at least 3 meter distance from HT cables . All temporary cables should be laid at least 750 mm below ground on 100 mm fine sand overlaying by brick soling.
Proper sleeves should be provided at road crossings.
Provide cable route markers indicating the type and depth of cables at intervals not exceeding 30 m and at the diversions termination.
2Working at HeightsPerson can fall downMay sustain severe injuries or prove fatalProvide guard rails / barricades at the work place
Use PPE like safety belts, full body harness, with two life lines , helmets , safety shoes etc.
Obtain work permit before starting the work at height above 2 meters.
Fall arrestor systems like safety nets must be installed
Provide proper working space ( min 0.6 m x 0.6 m)
Tie / weld working platform with fixed support.
Avoid moments on beams.
May hit the scrap / material stacked at the ground or in betweenKeep the work place neat and clean
Remove the scrap immediately
Material can fall downMay hit the workers working at lower levels & prove fatalSame as above plus
Barricade the area at ground level
Do not throw or drop materials or equipment from height.
All tools to be carried in a tool kit bag.
Remove scraps from the planks.
Ensure wearing of helmet by the workers at low level
3Confined SpacesSuffocationUnconsciousness / deathUse respiratory devices
Avoid over crowding inside a confined space
Provide exhaust fans / ventilation
Do not use loose clothes.
Keep a stand by person outside the vessel
Provide alarm bell to the person inside the confined space.
Check for reasons of hydro carbons O2 level, toxic gases
Obtain permit before entering the confined space
All incoming lines to the tank should be emptied and blank
Presence of foul smell and toxic substancesInhalation can pose threat to lifeSame as above plus Check for compounds before entering a confined space
Keep one person outside the confined space for continuing monitoring and for extending help in case of emergency.
Ignition / flame can cause firePerson may sustain burr injuries or explosion may occurKeep fire extinguishers handy
Remove surplus material and scrap immediately
Do not smoke inside a confined space
Do not allow gas cylinders inside a confined space
Use low voltage (24 V) explosion proof lamps for lighting
Use pneumatic tools or electric tools with max. 24 V (explosion proof)
Remove all equipments at the end of the day.
4RadiographyIonizing / radiation from sourceRadiation may cause diseases like cancer , skin irritation , dermatitis etcFollow safety guidelines from BARC before commencement of job.
Employ authorized and trained person with requisite qualifications.
Barricade the area and install radiation warning symbol.
Restrict the entry of unauthorized persons.
Wear appropriate PPE and film badges issued by BARC.
Transportation and storage of radiography sourceSame as aboveNever touch or handle radiography source with hands.
Store radiography source inside approved pit in an exclusive isolated storage room with lock and key arrangement.
Radiography source shall never be carried in a passenger bus or an passenger compartment of train.
BARC should be informed before source movement.
Loss of radioisotopeSame as aboveTry to locate with the help of survey meter and inform to BARC
5Hand Power ToolsUnguarded moving parts like grinding wheels, drill bits.It may injure the operator. Wheel may get detached,. And hit the passer might by flying missiles causing serious injury.Use proper guard. Ensure tightening mechanism of the tool.
Supply of power without earthingElectrocutionAlways use three pin plug. Ensure good earthing.
Damage toolsCan cause injury.Always use tested & verified tools.
6Lifting Activities.Failure of load lifting & moving equipmentCan cause accident & proved to be fatalCheck periodically oil, brakes, gears, Horns , and tyre pressure of all moving machinery, Check quality, size & condition of all chained pulley blocks, sleeves, Sling, U clamps, D shackle , wire ropes, etc. Allow crane to move only on hard firm and leveled ground . Allow lifting sling as short as possible.
Overloading of Lifting equipments.Same as aboveSafe Lifting capacity of derricks, and winches should be ascertained, Maximum SWL shall marked on all lifting equipments. Check the weight of columns & other heavy items painted on them and accordingly design above the angle of erection. Allow only trained operators and riggers during crane operations.
Overhead Electrical wiresCan cause electrocution & fire. Do not allow boom or the other part of the crane to come within the three meter reach of overhead HT cables.
Hook & load being lifted shall be preferably remained in full visibility.